Technology: |
|
|
|
|
1. Expansion of live game sound into concourse restrooms |
$ |
601,000 |
2. New HD Video Display system to east end zone |
|
8,764,000 |
|
3. Expanded video control room including full conversion to High Definition |
|
5,092,000 |
|
4. Upgraded Tele/Data infrastructure to meet modern requirements |
|
6,604,000 |
|
5. New data distribution system to support IPTV and distributed TV monitors |
|
4,194,000 |
|
$ |
25,255,000 |
||
|
|
|
|
Upgrades – Ingress, Egress, Circulation, Restrooms and Food Service: |
|
|
|
6. East End Zone Renovation including main concourse expansion and addition of a new commissary building |
$ |
8,331,000 |
|
7. Intentionally Omitted. |
|
|
|
|
8. Intentionally Omitted. |
|
|
|
9. New destination concession and restroom areas on the upper concourse |
|
4,442,000 |
|
|
$ |
12,773,000 |
|
|
|
|
Branding - Front Profile, Team Store, Way finding and Sponsor Activations Plaza: |
|||
|
10. Relocation and expansion of Team Store to the new west end plaza |
$ |
2,641,000 |
|
11. New stadium entry plazas including wrought iron security fence |
|
7,108,000 |
|
12. Steel canopies for new stadium entry plazas |
|
1,083,000 |
|
13. Enhanced graphics and way finding throughout entire stadium and gates |
|
3,197,000 |
|
|
$ |
14,029,000 |
|
|
|
|
Thorough Renovation of Present Space: |
|
|
|
14. Various infrastructure repairs and maintenance items |
$ |
10,451,000 |
|
15. Refurbish and enhance existing press box area |
|
706,000 |
|
16. Concourse life safety improvements to enhance code compliance |
|
1,195,000 |
|
|
17. Install galvanized intermediate aisle rails in upper bowl |
|
954,000 |
18. New fire alarm detection and notification system in Training Facility |
|
210,000 |
|
19. Add ADA compliant wheelchair seating in 300 level seating areas |
|
165,000 |
|
20. Add ADA compliant wheelchair seating in east and west end zones |
|
609,000 |
|
21. Install handrails on both sides of vomitory ramps on main concourse |
|
1,011,000 |
|
22. Cosmetically upgrade and refurbish all existing toilet rooms |
|
3,938,000 |
|
23. Renovate concession stands to meet modern requirements |
|
4,067,000 |
|
24. New equipment for renovated concession stands |
|
3,923,000 |
|
|
25. Deploy full POS system for all existing and new concession stands |
|
1,564,000 |
|
26. Renovation of post-game interview room, field tunnel and storage areas |
|
835,000 |
|
27. Intentionally Omitted |
|
|
|
28. Upgraded lighting throughout the main concourse |
|
797,000 |
|
29. Relocate writing press to tower club and convert old press box to 50 yard line club |
|
2,256,000 |
|
30. Repurpose operations area to field level staging area |
|
1,012,000 |
|
31. Cosmetically upgrade stadium suites |
|
5,760,000 |
|
32. Add radiant heat to sideline club seats and newly added areas of main and upper concourse |
|
966,000 |
|
33. Renovation of Time Warner tower club area |
|
1,606,000 |
|
34. Intentionally Omitted |
|
|
|
35. Enhanced tailgate experience in parking lots |
|
637,000 |
|
|
$ |
42,662,000 |
Team Areas: |
|
|
|
|
36. Training facility modernization through expansion and upgrades |
$ |
7,684,000 |
|
37. New operations and storage complex |
|
3,707,000 |
|
|
$ |
11,391,000 |
|
|
|
|
|
SUB - TOTAL: |
$ |
106,110,000 |
|
A/E Fees: |
$ |
8,519,000 |
|
Other Soft Costs: |
$ |
2,371,000 |
|
PROJECT CONTINGENCY RESERVES: |
$ |
13,000,000 |
|
|
|
|
|
TOTAL: |
$ |
130,000,000 |