Black Rock Canal Capital Improvements

Black Rock Canal Park

2012 - 2017 Capital Improvements:


Project Name

Problem/Issue

Type of Work Completed

  Cost to Complete

 

Phase 2 Improvements

Phase 2 will include parking lot improvements and amenities.

Parking lot improvements—under design and work to in 2014.

$350,000.00

(County Share)

Dock safety related concerns

Investigation of dock at BRCP suggested to block off for public access until replaced.

Vendor fenced/blocked off dock area assuring public cannot gain access until Phase 2 is completed.

$2,150.00

                                                                                                                                                                                      TOTAL: $352,150.00