Isle View Park
2012 - 2021 Capital Improvements:
Project Name |
Type of Work Completed |
Estimated Cost to Complete
|
Domestic Violence Tribute Garden |
Phase 1 of Domestic Violence Tribute Garden. Wall, Stone work and site work as part of Phase 1. |
$20,000.00 |
Plumbing Upgrade |
Work needed to upgrade/ meet code. Upgrades and line extension to concessionnaire building, including method to drain/winterize yearly. |
$3,995.00 |
Parking Lot & Roadway Improvements- Phase 2 |
Continue efforts to improve areas within park that are in poor condition/ shape. Various sections of the River Walk were paved. |
$89,404.00 |
Maintenance Shop Roof |
Age and overall poor condition. Roof completely torn off and replaced. |
$124,000.00 |
Parking Lot & Roadway Improvements - Phase 2 |
Continue efforts to improve areas within park that are in poor condition/ shape. Additional sections of the River Walk were paved. |
$4,950.00 |
Total: $222,349.00