2012 - 2021 Capital Improvements:

 

  Project Name

Type of Work Completed

 Estimated Cost to Complete

 

Parking Lot & Roadway Improvements

Several areas throughout park are in poor condition and need to be resurfaced. Two (2) DI’s Repaired, Maintenance Lot resurfaced and roadway near shelter #1 repaired (various patching).

$28,577.00

Tennis Court Repairs/Resurfacing

All four (4) courts are experiencing major cracks and surface related issues. Resurfacing, painting and all new hardware.

$78,875.00

Parking Lot & Roadway Improvements- Phase 2

Continue efforts to improve areas within park that are in poor condition/ shape. Aprons paved around comfort stations "A" and B" in the camping area

$8,307.00

Chlorinator Upgrade

Chlorinator for campgrounds broke down. Water is no longer potable. Chlorinator upgraded

$4,198.00

Campsite Upgrade

More electric campsites needed. Converted thirty-two (32) non-electric campsites into electric.  

$229,548.00

“A” Comfort Station Roof

Roof needed replacement. New roof shingles installed.

$5,764.00

Fire Alarm Upgrade

Current fire alarm system outdated and inadequate. New fire alarm system installed.

$4,500.00

 

“A” & “B” Comfort Station Renovations

Restrooms needed complete renovation. New lighting and doors installed. Showers re-tiled. Restrooms painted.

$97,921.00

"A" & "B" Camping Restrooms

Floors needed replacing. New TIle Floors Installed

$21,800.00

Upper Camping Loop Sanitary System

New Lift Pumps and Electrical Panel Installed

$25,500.00

                                                                                                                                                                                    TOTAL: $504,990.00